|
Australia Telescope National Facility Memorandum |


To: ATUC/ATSC
From: Director
Subject: ATUC response
Date: 17
February 2004
The
Director’s response to the ATUC report from the previous meeting is a standing
item at each ATUC meeting. The meeting
schedule for ATUC (December and June) and ATSC (March/April) is such that there
is an opportunity for the ATNF Director to provide comprehensive feedback on
the ATNF’s progress towards achieving some of the recommendations/actions
contained in the main (December) ATUC report to ATSC at their meeting. [Note
that the provision of a report by ATUC to the ATSC is now included in the
formal terms of reference for ATUC (see below).
As a committee appointed by the ATSC, it is appropriate that the ATSC
formally approve these ToR.]
In
common with the approach adopted for the Director’s response to the steering
committee actions I propose a ‘monochrome’[1] traffic
light evaluation of ATNF’s response to the ATUC recommendations. The symbols
against each non-trivial action/recommendation are as follows:
![]()
Action done/recommendation adopted.
(18)
![]()
Action attempted or still ongoing,
recommendation partially adopted (10)
![]()
Action not attempted, recommendation
not adopted (2)
Numbers
in parentheses indicate numbers of actions/recommendations evaluated to fall in
each category. ATUC are welcome to
change any of these evaluations as the see appropriate.
It
would be appropriate for the ATSC to define a goal for the fraction of “grey”
and “black” traffic lights reported back at each meeting as a measure of the
Director’s performance in implementing the User Committee’s recommendations.
It
is recommended that the User Committee
It
is recommended that the Steering Committee
|
ATUC
Comments |
Director’s
response |
||||||||||||||||
|
3.5 Terms of Reference Prior to the
meeting the ATNF Director provided draft ATUC Terms of Reference for
consideration by ATUC. ATUC endorsed
the draft Terms of Reference with a few minor alterations and an additional
item outlining the membership structure of the committee. The revised
suggested ATUC Terms of Reference follow:
|
|
||||||||||||||||
5.1 Operational PlanATUC endorses the
03-04 Operational plan. ATUC will compile advice on the 04-05 Operational Plan
and make it available to the Director. |
|
||||||||||||||||
5.4 Project ManagementATUC strongly
endorses the implementation of co-ordinated project management practices and
believes that they will add to the efficiency and success of ATNF projects,
with benefits for the ATNF and users. |
|
||||||||||||||||
5.5 SKA/LOFARATUC are happy to
see a high degree of coordination between the LOFAR and SKA projects within
the ATNF, since this
will allow an efficient use of limited resources. However, ATUC will reserve discussion or
comment on the level of ATNF participation in LOFAR until the LOFAR Options
Paper becomes available. ATUC do not
feel that they have sufficient information available to discuss this issue in
an informed fashion at this time. |
|
||||||||||||||||
|
6.1 Six month semesters |
|
||||||||||||||||
|
For ATUC position see report. |
|
||||||||||||||||
|
What do ATUC think of a Triage system? ATUC sees little
value in the triage process for the current level of over-subscription. ATUC
request that users be fully informed of changes that are made to the proposal
evaluation process. |
The TAC will
therefore trial a triage system at the next meeting, scheduled for March
2004. Proposers will
continue to receive TAC grades and comments. Users will be fully informed of
the triage system at the next ATUC meeting. |
||||||||||||||||
|
Does ATUC have any view as to when
deadlines for six-month terms should fall? ATUC recommend
the following dates for the new six-month semesters: Proposals TAC Sched Start End Due Meets out Term Term 1 Dec 15 Jan 15 Feb 15
Mar 31 Aug 1 Jun 1 July 1 Aug 1
Sept 14 Mar Considering: 1. The September
1 start gives mm users opportunities in both semesters and provides
flexibility in the important first mm season for the new system. This allows
the Australian mm community to be responsive to new science opportunities and
a rapidly evolving 3mm system at the ATCA. 2. These dates
also meet the needs of new students and post-docs commencing early in the
year who might otherwise have to wait another 12 months to propose for mm
observations. 3. This takes
into account Australian university semesters so that proposal deadlines occur
during term breaks and don't coincide with ARC deadlines. 4. This takes
into account transition issues such as allowing users time to adjust and plan
for six month terms. 5. Four month
terms should remain until the September 1 semester. The last proposal
deadline for four month terms will be 15 Feb and the first proposal deadline
for six month terms will be June 1. 6. This proposal
is consistent with the ATNF meeting schedule and allows adequate time for the
TAC to meet and OICs to produce schedules. If ATNF require
any further user input, ATUC would be happy to consult further on the details
and we strongly encourage ATNF to keep ATUC informed in the
implementation of six month semesters. |
1. It is not feasible to hold a TAC meeting
between mid-December and end-January due to the holiday season. 2. The proposed term lengths are unequal –
with a shorter 5.5 month term over the winter months when demand for ATCA
facilities is likely to be greatest. This would create an imbalance in the
oversubscription rate between the two semesters and would require additional
effort to reconcile our key performance indicators. After
consultation with both ATUC and TAC, and careful reconsideration of all the
issues, the ATNF has decided to move to six month semesters with application
deadlines on June 01 and Dec 01, for semesters that begin on Oct 01 and April
01. For the
transition period, the dates for the next three terms will be as follows:
Notes: ·
The
two semesters are of equal length ·
The
TAC will review proposals over the Xmas period and will meet in early
February ·
The
deadlines are well suited to new students and
to the Australian universities ·
Some
limited millimeter observing will be available for 3-4 weeks in October. ·
The
deadline on Feb 15 will be for a five-month Term (May to Sep). The first six month term will begin on Oct
01 |
||||||||||||||||
|
Director's time ATUC would like
to see a clarification on the purpose of discretionary time. Time is already
available in the ATCA and Parkes schedules for observers who lose time, for
commissioning instruments and for testing purposes. Processes are in place
for scheduling unallocated time and ATUC don't see any reason for
discretionary time given the amount of unallocated time currently available.
ATUC are unclear as to whether the idea of discretionary time applies to all
facilities or just the ATCA. What
would be the rules for allocating discretionary time? If these rules are
substantially different from existing rules for unallocated time, ATUC are
concerned that this might act as a disincentive for Duty Astronomers, who
currently have first priority to unallocated time after observatory
requirements. |
The The ATSC has
recommended that 5% of time on ATNF facilities should be scheduled at the
Director’s discretion. At present, around 10% of time at Parkes and the
Compact Array is unallocated in the initial schedules. The use of this time
is specified as (i) OIC discretion, (ii) maintenance (other than regular
maintenance), (iii) DA, (iv) local staff, (v) other observers. In the light of
ATUC’s comments the following resolution was put to the TAC at their March
meeting: With effect from May 1, all unallocated time at the Compact Array and
Parkes will be designated as Director's time. The ATNF Director will have
overall authority for the allocation of this time. In most cases this will
scheduled according to previously established priorities: 1. OIC discretion (targeted opportunities, lost time replacements), 2.
Repairs (other than regular maintenance), 3. Duty astronomer, 4. Local staff,
e.g. adjacent observers, 5. Other observers present on-site, 6. Remote
observers Applications to use this time should be directed in the first instance
to the relevant OiC, via the existing application process. In addition, one or two longer blocks of typically 12 hours may be scheduled each month as Director's time, provided that the total amount of Director's time does not exceed 10% in any one semester. Opportunities to use this time will be advertised to the user community as appropriate and applications submitted to the Director. |
||||||||||||||||
|
8.1 ATCA/Mopra report Can ATUC suggest ways in which Mopra can be more heavily used by Australian users? [question from ATNF] ATUC suggest that
ATNF facilitate some Key Science Projects. For example a multi-line targeted
survey with the new wide band spectrometer that could be run using the very
successful HIPASS project as a model.
There will be a Millimetre Workshop in December and a session will be
devoted to new large projects with Mopra.
Also, it seems likely that the implementation of reliable remote
observing for Mopra would increase usage.
ATUC suggest that implementation of remote Mopra observing could be
brought forward to the 2004 winter, so that Mopra can be utilised in
conjunction with the first observations of the full 3 mm system at the ATCA |
|
||||||||||||||||
|
8.2. Users’ Guide What is the
status of the updated Users Guide that was recently being edited by Jess
O'Brien? |
Updated users’ guide is now available and
on the WWW. |
||||||||||||||||
|
9.2 Opera House ATUC would like
to see the new areas converted to office space for observers and visitors,
with computer facilities for data reduction, network connections for laptops
etc. |
|
||||||||||||||||
|
9.3 Parkes Receivers ATUC noted queries
from users on the timescales for planned upgrades to Parkes receivers. ATUC are encouraged by the potential 4dB improvement to the
12 mm system at Parkes and still consider this to
be the first priority receiver for serious upgrade at Parkes. Will this upgrade be possible before the
start of the 2004 winter season? ATUC would also
like see the H-OH receiver upgraded with the Arecibo LNA's in the near term.
Apparently this is not considered to be a large job. Could ATNF comment on the possibility of
performing this upgrade before the start of the January term? |
Major receiver
projects at Parkes undertaken in 2003/04 include; · refurbishment
of the AT Multiband receiver (complete) · commissioning
of the 8GHz (MARS) receiver (complete) · · rectification
and RFI mitigation of 10/50cm receiver (ongoing) · refurbishment
of the 21cm Multibeam receiver (in progress) ·
refurbishment of H-OH receiver (complete) ·
construction of 7-beam 6GHz receiver (Marsfield
project: in progress). The ATNF sees the
next priority as upgrading the K-band (22GHz) capability. It has not been
possible to initiate this project yet, largely due to uncertainties in, and
priority of, the 21 cm refurbishment project. A detailed project
plan for receiver upgrades will be distributed at or before the next ATUC
meeting.
The upgraded
receiver has 20% improved performance at 1.4GHz (33Jy SEFD v. 40Jy), much
closer to the that of the 21cm Multibeam centre-beam (30Jy), but with
considerably wider overall bandwidth. The upgraded receiver also has improved
stability and gain properties. |
||||||||||||||||
|
10.1 Tidbinbilla Does ATUC see the need for a mapping mode at
Tidbinbilla? If so, when would they like to see it implemented? [question from ATNF] ATUC sees great
value in a mapping mode at such a powerful telescope and a significant
potential demand. ATUC recommend that a spectral-line mapping mode be
implemented as soon as possible, since on the advice of Jim Lovell this seems
to be not such an onerous task. ATUC also request that Jim Lovell look into
options for total power mapping and beam switching and report back to ATUC
with a realistic timescale for implementation of this additional mapping
mode. |
New antenna
control software will need to be written and tested. The current milestone is
the end of May at which point the system will be able to scan a region of sky
while collecting data from the correlator. This will provide a basic
spectral-line mapping capability.
|
||||||||||||||||
|
11.1 LBA report ATUC feel that
access to New Norcia would improve the operation of the LBA and request that
Tasso Tzioumis provide a more detailed plan for access to this antenna at the
next meeting. For example, is the aim with New Norcia to
negotiate an agreement with ESA for access? What work is required to get the
antenna ready for astronomical observations, apart from the provision of a
data recording system as outlined in item 17.4 below? |
|
||||||||||||||||
|
12.2 Time Usage Statistics ATUC request that
the ATNF provide ATUC the same proposal statistics that the Steering
Committee receive, as outlined under agenda item 3.4, action 8, of the Actions
and Recommendations of the ATNF Steering Committee, July 2003. [request by
ATUC] These statistics
should ideally include a breakdown of proposals for overseas, ATNF, and other
Australian proposers (by country for overseas proposals and by institute for
other Australian), into the following categories, for each facility:
|
|
||||||||||||||||
|
13.1 Software Report ATUC encourage
the ATNF to pursue the MOU for aips++, potentially with a view to
long-term maintainance of the project.
[statement by ATUC] |
The main goal of
the agreement is to ensure that all those working on aips++ remain informed
of each others’ activities, and do not compromise each others
activities. Joint planning will be undertaken where appropriate (e.g.
infrastructure changes) and work tradeoffs will be negotiated. ATNF is now highly
focussed on developing applications with aips++ for its own needs. ATNF
will continue to do some infrastructure work as needed (e.g. upgrade
Coordinates to new WCS FITS standards). |
||||||||||||||||
|
13.2 SPC replacement ATUC would like
to reinforce their previous statements that they consider the planned SPC
replacement a very high priority. ATUC
are encouraged by the outlined plan for the SPC replacement and look forward
to a report on the expected progress toward this goal at the next ATUC
meeting. |
|
||||||||||||||||
|
13.3 Online archive ATUC notes
comments from users that to be really useful, the ATCA data archive will need
to record information from the observing system. [Issue raised by users] ATUC recognise
that the ATNF is well aware of this issue. ATUC suggest that on-line
logging of ancillary data be implemented at the ATNF telescopes as part of
any data archives. A simple filtering of existing electronic logs might
be a useful first step and should be incorporated into future observing
software upgrades, especially as Linux becomes more pervasive throughout
observing systems. |
|
||||||||||||||||
|
13.4 Miriad Support ATUC would like
clarification on who is providing the 0.2 FTE support for MIRIAD. It appears
that support for MIRIAD has decreased. Given that MIRIAD is a mission
critical package for the ATNF, we encourage that it be continually supported
at a reasonable level i.e. timely responses to bug reports, supported
compatibility with new computers and new versions of Linux operating systems. |
|
||||||||||||||||
|
13.5 ssh ATUC notes
comments from users that the lack of the ssh2 software on ATNF computers is
making difficult to connect to outside institutions. [Issue raised by users]
ATUC requests that ssh2 be installed on the ATNF Unix computers. |
ATNF acknowledges
the frustration felt by many users.
A recent meeting
between ATNF and senior CSG personnel has established firm milestones for a
number of key IT issues that has languished for some time. These include: · Solaris
upgrades · Linux
support (mainly laptops) · Browser
upgrades ·
ssh upgrade ·
User account name change over (to CSIRO ident) In particular, the
ssh upgrade process will be much simplified by the Solaris upgrade. The
present milestone is that the Solaris upgrade will be completed by June
2004. ATNF has also asked CSG to produce (by end March 2004) a plan to
implement ssh2 immediately following the Solaris upgrade. |
||||||||||||||||
|
15.1 Technology Development Report ATUC propose to
undertake a review of all projects before the next ATUC meeting. At this
meeting ATUC will be willing to advise the ATNF on projects that have such a
low priority, in the users view, that they can be dropped from this list.
Would the ATNF consider this to be useful input from the ATUC? |
ATUC’s comments would be indeed be valued
as part of the priority setting process for new projects. |
||||||||||||||||
|
16.1 Wide band correlator for Tidbinbilla ATUC suggest that
ATNF explore the option of sharing the yet-to-be-constructed wide-band Mopra
correlator between Mopra and Tidbinbilla, as an alternative to building two
correlators, which will occupy a significant amount of precious time for key
engineering personnel. It seems to
ATUC that, if possible, sharing a wide-band correlator over the winter season
between Mopra and Tidbinbilla may satisfy the demand for such an instrument
on both antennas. ATUC would like to
see an analysis of the shared correlator idea at its next meeting. |
|
||||||||||||||||
|
16.2 EoR instrument ATUC can see the
value in such an instrument but feel that the scale of the project is more
suited to a collaboration between the ATNF and a university department,
funded possibly via the ARC. Regardless of the funding, this project could
require a significant amount of ATNF engineering effort, which currently is
the limiting factor in prioritising new projects. ATUC suggests that engineering support for
this project could also be found outside the ATNF, through collaboration with
a university department. This project
should therefore be a low priority for the ATNF. |
|
||||||||||||||||
|
16.3 SUSI delay line ATUC also think
that this is a very interesting and novel idea. However it appears that this project will
be soon rivaled by the planned upgraded wide-band ATCA correlator and any
resources would be better spent on this larger and higher priority project. |
|
||||||||||||||||
|
16.4 Portable VLBI terminal This project
should be considered as part of a broader upgrade to LBA facilities. New
hardware for New Norcia should only be considered after negotiation with ESA
for access to the antenna. |
|
||||||||||||||||
|
16.5 Pulsar digital filter bank This project
should have priority over the upgrade of the existing pulsar correlator to
high time resolution. ATUC will review
the overall priority of this project along with other existing projects,
before the next ATUC meeting. |
|
||||||||||||||||
|
16.6 Faraday/PHAROS ATNF should
provide a project scientist to develop an initial science case, in the event
that no especially interested person from the user community steps forward to
provide a justification for these instruments. More information on the frequency range
that these instruments might operate over would be useful. ATUC will review the overall priority of
this project along with other existing projects, before the next ATUC
meeting. |
|
||||||||||||||||
|
16.7 HIFAR This is a very
large project. The scientific and
technical case for HIFAR should be developed further, in particular how it
aligns with LOFAR and the SKA. ATUC
will review the overall priority of this project along with other existing
projects, before the next ATUC meeting. |
|