 +====== ​ VLBI teleconference,​ 20 May 2010 ======
 +=====  12.00 Perth, 14.00 Eastern, 16.00 New Zealand =====
 +
 +Phone:
 +
 +| Vic:|03 9545 8222 |
 +| NSW:|02 9490 8022 |
 +| ACT:|02 6276 6622 |
 +| Qld:|07 3214 2311 |
 +|  WA:|08 6436 8844 |
 +|  SA:|08 8273 8122 |
 +|  NT:|08 8944 8488 |
 +| Tas:|03 6232 5188 |
 +Meeting ID: 1524
 +
 +Chair: Tasso Tzioumis
 +
 +Attendance: Shinji Horiuchi (SDCCC, Canberra); Bruce Stansby, Cormac Reynolds, Hayley Bignall (Curtin); Tasso Tzioumis, Chris Phillips, Phil Edwards (ATNF Marsfield); ​ Brett Reid, Jamie McCallum (UTas, Mt. Pleasant); Richard Dodson. Maria Rioja (UWA) 
 +
 +
 +**Agenda**
 +
 +SPECIAL ​ - DEBRIEF FROM MAY10 VLBI SESSION
 +
 +  *  Reports from observatories
 +    *  ATCA phasing
 +  *  Issues for/from correlator
 +  *  Any other issues
 +
 +  *  Next VLBI session in July (22-27)
 +
 +**Actions arising**  ​
 +
 +** * Previous actions were not reviewed. Tasso to review and consolidate actions from previous meetings, and bring for discussion at next meeting. (Tasso) **
 +
 +  *  Implement DAS automatic cable changing for 64 MHz/16 MHz (Chris, atnf staff)
 +  *  Investigate and understand timing issues with the CABB and DAS at atca (Jamie, Chris, ATNF)
 +  *  Investigate issues with daemon services at Mp system (Tasso, Chris)
 +  *  For Parkes receiver changes ensure that Ettore is consulted (ATNF, Ettore)
 +
 +  *  Investigate issues with RF hybrid and polarisation on Warkworth antenna (Tim)
 +
 +
 +  *  Check XRAIDs on station before session start (UTas)
 +  *  Revise Hobart procedures on xraid changes to spped up fringe testing(UTas)
 +  *  Upgrade recorderserver at Ho and Cd (UTas, Jamie Stevens, Chris)
 +  *  Document and investigate using the Hobart HEX cluster as backup recorder for VLBI (UTas)
 +
 +  *  Coordinate schedules to ensure all telescaopes start at known state/wrap (ALL)
 +
 +
 +  *  Investigate CSIRO plans re 1 Gbps connectivity to Tid (Tasso)
 +  *  Telecon between ATNF and NZ to sort out NZ network issues (Shaun, Chris, Tim, AUT)
 +
 +  *  Check 22 GHz polarisation results from last session (Correlator,​ Richard, PI...)
 +
 +  *  Recommendations for PIs to include calibrators to phase-up atca (ATNF)
 +
 +  *  RTFC upgrade is need for 64 MHz. Need to go to DiFX 2.0. Moderate project. (Chris)
 +
 + 
 +
 +Next meeting: Early July, prior to next session
  