Line 96: Line 96:
     *  Evaluate results of test with Rb vs H-maser at S-band during LBA session (UTas, CASS, Curtin)     *  Evaluate results of test with Rb vs H-maser at S-band during LBA session (UTas, CASS, Curtin)
  
-  *  Check with NZ re issues with Ww drivs (Tasso)+  *  Check with NZ re issues with Ww drives ​(Tasso)
  
   *  Implement larger filesizes for recording (1 minute) since number of files is impacting the PB store (Chris, Jamie)   *  Implement larger filesizes for recording (1 minute) since number of files is impacting the PB store (Chris, Jamie)
Line 113: Line 113:
  
   *  Graham Jenkins is leaving VPAK. need to make new arrangements. Check with VPAK systems manager Craig West (Tasso)   *  Graham Jenkins is leaving VPAK. need to make new arrangements. Check with VPAK systems manager Craig West (Tasso)
- 
-  *  Check with AARNet re network access to MRO for March (Tasso) 
- 
-  *  Next LBA annual operations meeting in Marsfield on 21-22 Feb 2012 for full 2 days. To include networking session and VLBA 1/2 day (Tasso) 
-    *  need text re VLBA discussion (Cormac) 
-    *  Check with Phil Diamond and Steven Tingay re VLBA access (Tasso) 
  
   *  Test new DiFX fixes for mixed-band mode. (Cormac)   *  Test new DiFX fixes for mixed-band mode. (Cormac)
Line 131: Line 125:
   *  Remind Shaun re extra disks for LBA archive. (Tasso)   *  Remind Shaun re extra disks for LBA archive. (Tasso)
  
 +  *  Ceduna to get new MK5C + dBBC and Ho 26m a MK5B. Need to integrate Mk5 monitoring into LBA. (UTas, Jamie S.)
  
 +
 +  *  Check with AARNet re network access to MRO for March (Tasso)
 +
 +  *  Next LBA annual operations meeting in Marsfield on 21-22 Feb 2012 for full 2 days. To include networking session and VLBA 1/2 day (Tasso)
 +    *  need text re VLBA discussion (Cormac)
 +    *  Check with Phil Diamond and Steven Tingay re VLBA access (Tasso)
 +    *  Check for AARNet participation (Tasso)
  
 Next meeting: LBA operations meeting. 21-22 February 2012. CASS at Sydney. Next meeting: LBA operations meeting. 21-22 February 2012. CASS at Sydney.
  