Australia Telescope National Facility Memorandum |
To: ATUC/ATSC
From: Director
Subject: ATUC response
Date: 17 February 2004
Background
The Director’s response to the ATUC report from the previous meeting is a standing item at each ATUC meeting. The meeting schedule for ATUC (December and June) and ATSC (March/April) is such that there is an opportunity for the ATNF Director to provide comprehensive feedback on the ATNF’s progress towards achieving some of the recommendations/actions contained in the main (December) ATUC report to ATSC at their meeting. [Note that the provision of a report by ATUC to the ATSC is now included in the formal terms of reference for ATUC (see below). As a committee appointed by the ATSC, it is appropriate that the ATSC formally approve these ToR.]
In common with the approach adopted for the Director’s response to the steering committee actions I propose a ‘monochrome’[1] traffic light evaluation of ATNF’s response to the ATUC recommendations. The symbols against each non-trivial action/recommendation are as follows:
Action done/recommendation adopted. (18)
Action attempted or still ongoing, recommendation partially adopted (10)
Action not attempted, recommendation not adopted (2)
Numbers in parentheses indicate numbers of actions/recommendations evaluated to fall in each category. ATUC are welcome to change any of these evaluations as the see appropriate.
It would be appropriate for the ATSC to define a goal for the fraction of “grey” and “black” traffic lights reported back at each meeting as a measure of the Director’s performance in implementing the User Committee’s recommendations.
Recommendations
It is recommended that the User Committee
- Endorse the Director’s responses to their actions/recommendations from the 2003 report
- Agree, incorporating any revisions, with the ‘traffic light’ evaluation provided
It is recommended that the Steering Committee
- Approve, with any revisions, the proposed ATUC Terms of Reference below
- Make the Director’s response to the ATUC December report a standing item on the ATSC agenda.
- Adopt an appropriate goal for the maximum fraction of ‘grey’ and ‘black’ traffic lights reported in this response.
ATUC Comments |
Director’s response |
||||||||||||||||
3.5 Terms of Reference Prior to the meeting the ATNF Director provided draft ATUC Terms of Reference for consideration by ATUC. ATUC endorsed the draft Terms of Reference with a few minor alterations and an additional item outlining the membership structure of the committee. The revised suggested ATUC Terms of Reference follow:
|
|
||||||||||||||||
5.1 Operational PlanATUC endorses the 03-04 Operational plan. ATUC will compile advice on the 04-05 Operational Plan and make it available to the Director.
|
|
||||||||||||||||
5.4 Project ManagementATUC strongly endorses the implementation of co-ordinated project management practices and believes that they will add to the efficiency and success of ATNF projects, with benefits for the ATNF and users. |
|
||||||||||||||||
5.5 SKA/LOFARATUC are happy to see a high degree of coordination between the LOFAR and SKA projects within the ATNF, since this will allow an efficient use of limited resources. However, ATUC will reserve discussion or comment on the level of ATNF participation in LOFAR until the LOFAR Options Paper becomes available. ATUC do not feel that they have sufficient information available to discuss this issue in an informed fashion at this time. |
|
||||||||||||||||
6.1 Six month semesters |
|
||||||||||||||||
For ATUC position see report. |
|
||||||||||||||||
What do ATUC think of a Triage system? ATUC sees little value in the triage process for the current level of over-subscription. ATUC request that users be fully informed of changes that are made to the proposal evaluation process. |
The TAC will therefore trial a triage system at the next meeting, scheduled for March 2004. Proposers will continue to receive TAC grades and comments. Users will be fully informed of the triage system at the next ATUC meeting. |
||||||||||||||||
Does ATUC have any view as to when deadlines for six-month terms should fall? ATUC recommend the following dates for the new six-month semesters: Proposals TAC Sched Start End Due Meets out Term Term 1 Dec 15 Jan 15 Feb 15 Mar 31 Aug 1 Jun 1 July 1 Aug 1 Sept 14 Mar Considering:
1. The September 1 start gives mm users opportunities in both semesters and provides flexibility in the important first mm season for the new system. This allows the Australian mm community to be responsive to new science opportunities and a rapidly evolving 3mm system at the ATCA. 2. These dates also meet the needs of new students and post-docs commencing early in the year who might otherwise have to wait another 12 months to propose for mm observations. 3. This takes into account Australian university semesters so that proposal deadlines occur during term breaks and don't coincide with ARC deadlines. 4. This takes into account transition issues such as allowing users time to adjust and plan for six month terms. 5. Four month terms should remain until the September 1 semester. The last proposal deadline for four month terms will be 15 Feb and the first proposal deadline for six month terms will be June 1. 6. This proposal is consistent with the ATNF meeting schedule and allows adequate time for the TAC to meet and OICs to produce schedules. If ATNF require any further user input, ATUC would be happy to consult further on the details and we strongly encourage ATNF to keep ATUC informed in the implementation of six month semesters. |
1. It is not feasible to hold a TAC meeting between mid-December and end-January due to the holiday season. 2. The proposed term lengths are unequal – with a shorter 5.5 month term over the winter months when demand for ATCA facilities is likely to be greatest. This would create an imbalance in the oversubscription rate between the two semesters and would require additional effort to reconcile our key performance indicators. After consultation with both ATUC and TAC, and careful reconsideration of all the issues, the ATNF has decided to move to six month semesters with application deadlines on June 01 and Dec 01, for semesters that begin on Oct 01 and April 01. For the transition period, the dates for the next three terms will be as follows:
Notes: · The two semesters are of equal length · The TAC will review proposals over the Xmas period and will meet in early February · The deadlines are well suited to new students and to the Australian universities · Some limited millimeter observing will be available for 3-4 weeks in October. · The deadline on Feb 15 will be for a five-month Term (May to Sep). The first six month term will begin on Oct 01 |
||||||||||||||||
Director's time ATUC would like to see a clarification on the purpose of discretionary time. Time is already available in the ATCA and Parkes schedules for observers who lose time, for commissioning instruments and for testing purposes. Processes are in place for scheduling unallocated time and ATUC don't see any reason for discretionary time given the amount of unallocated time currently available. ATUC are unclear as to whether the idea of discretionary time applies to all facilities or just the ATCA. What would be the rules for allocating discretionary time? If these rules are substantially different from existing rules for unallocated time, ATUC are concerned that this might act as a disincentive for Duty Astronomers, who currently have first priority to unallocated time after observatory requirements. |
The The ATSC has recommended that 5% of time on ATNF facilities should be scheduled at the Director’s discretion. At present, around 10% of time at Parkes and the Compact Array is unallocated in the initial schedules. The use of this time is specified as (i) OIC discretion, (ii) maintenance (other than regular maintenance), (iii) DA, (iv) local staff, (v) other observers. In the light of ATUC’s comments the following resolution was put to the TAC at their March meeting: With effect from May 1, all unallocated time at the Compact Array and Parkes will be designated as Director's time. The ATNF Director will have overall authority for the allocation of this time. In most cases this will scheduled according to previously established priorities: 1. OIC discretion (targeted opportunities, lost time replacements), 2. Repairs (other than regular maintenance), 3. Duty astronomer, 4. Local staff, e.g. adjacent observers, 5. Other observers present on-site, 6. Remote observers Applications to use this time should be directed in the first instance to the relevant OiC, via the existing application process. In addition, one or two longer blocks of typically 12 hours may be scheduled each month as Director's time, provided that the total amount of Director's time does not exceed 10% in any one semester. Opportunities to use this time will be advertised to the user community as appropriate and applications submitted to the Director. |
||||||||||||||||
8.1 ATCA/Mopra report Can ATUC suggest ways in which Mopra can be more heavily used by Australian users? [question from ATNF] ATUC suggest that ATNF facilitate some Key Science Projects. For example a multi-line targeted survey with the new wide band spectrometer that could be run using the very successful HIPASS project as a model. There will be a Millimetre Workshop in December and a session will be devoted to new large projects with Mopra. Also, it seems likely that the implementation of reliable remote observing for Mopra would increase usage. ATUC suggest that implementation of remote Mopra observing could be brought forward to the 2004 winter, so that Mopra can be utilised in conjunction with the first observations of the full 3 mm system at the ATCA |
|
||||||||||||||||
8.2. Users’ Guide What is the status of the updated Users Guide that was recently being edited by Jess O'Brien? |
Updated users’ guide is now available and on the WWW. |
||||||||||||||||
9.2 Opera House ATUC would like to see the new areas converted to office space for observers and visitors, with computer facilities for data reduction, network connections for laptops etc. |
|
||||||||||||||||
9.3 Parkes Receivers ATUC noted queries from users on the timescales for planned upgrades to Parkes receivers. ATUC are encouraged by the potential 4dB improvement to the 12 mm system at Parkes and still consider this to be the first priority receiver for serious upgrade at Parkes. Will this upgrade be possible before the start of the 2004 winter season? ATUC would also like see the H-OH receiver upgraded with the Arecibo LNA's in the near term. Apparently this is not considered to be a large job. Could ATNF comment on the possibility of performing this upgrade before the start of the January term? |
Major receiver projects at Parkes undertaken in 2003/04 include; · refurbishment of the AT Multiband receiver (complete) · commissioning of the 8GHz (MARS) receiver (complete) ·
· rectification and RFI mitigation of 10/50cm receiver (ongoing) · refurbishment of the 21cm Multibeam receiver (in progress) · refurbishment of H-OH receiver (complete) · construction of 7-beam 6GHz receiver (Marsfield project: in progress). The ATNF sees the next priority as upgrading the K-band (22GHz) capability. It has not been possible to initiate this project yet, largely due to uncertainties in, and priority of, the 21 cm refurbishment project. A detailed project plan for receiver upgrades will be distributed at or before the next ATUC meeting.
The upgraded receiver has 20% improved performance at 1.4GHz (33Jy SEFD v. 40Jy), much closer to the that of the 21cm Multibeam centre-beam (30Jy), but with considerably wider overall bandwidth. The upgraded receiver also has improved stability and gain properties. |
||||||||||||||||
10.1 Tidbinbilla Does ATUC see the need for a mapping mode at Tidbinbilla? If so, when would they like to see it implemented? [question from ATNF] ATUC sees great value in a mapping mode at such a powerful telescope and a significant potential demand. ATUC recommend that a spectral-line mapping mode be implemented as soon as possible, since on the advice of Jim Lovell this seems to be not such an onerous task. ATUC also request that Jim Lovell look into options for total power mapping and beam switching and report back to ATUC with a realistic timescale for implementation of this additional mapping mode. |
New antenna control software will need to be written and tested. The current milestone is the end of May at which point the system will be able to scan a region of sky while collecting data from the correlator. This will provide a basic spectral-line mapping capability.
|
||||||||||||||||
11.1 LBA report ATUC feel that access to New Norcia would improve the operation of the LBA and request that Tasso Tzioumis provide a more detailed plan for access to this antenna at the next meeting. For example, is the aim with New Norcia to negotiate an agreement with ESA for access? What work is required to get the antenna ready for astronomical observations, apart from the provision of a data recording system as outlined in item 17.4 below? |
|
||||||||||||||||
12.2 Time Usage Statistics ATUC request that the ATNF provide ATUC the same proposal statistics that the Steering Committee receive, as outlined under agenda item 3.4, action 8, of the Actions and Recommendations of the ATNF Steering Committee, July 2003. [request by ATUC] These statistics should ideally include a breakdown of proposals for overseas, ATNF, and other Australian proposers (by country for overseas proposals and by institute for other Australian), into the following categories, for each facility:
|
|
||||||||||||||||
13.1 Software Report ATUC encourage the ATNF to pursue the MOU for aips++, potentially with a view to long-term maintainance of the project. [statement by ATUC] |
The main goal of the agreement is to ensure that all those working on aips++ remain informed of each others’ activities, and do not compromise each others activities. Joint planning will be undertaken where appropriate (e.g. infrastructure changes) and work tradeoffs will be negotiated. ATNF is now highly focussed on developing applications with aips++ for its own needs. ATNF will continue to do some infrastructure work as needed (e.g. upgrade Coordinates to new WCS FITS standards). |
||||||||||||||||
13.2 SPC replacement ATUC would like to reinforce their previous statements that they consider the planned SPC replacement a very high priority. ATUC are encouraged by the outlined plan for the SPC replacement and look forward to a report on the expected progress toward this goal at the next ATUC meeting. |
|
||||||||||||||||
13.3 Online archive ATUC notes comments from users that to be really useful, the ATCA data archive will need to record information from the observing system. [Issue raised by users] ATUC recognise that the ATNF is well aware of this issue. ATUC suggest that on-line logging of ancillary data be implemented at the ATNF telescopes as part of any data archives. A simple filtering of existing electronic logs might be a useful first step and should be incorporated into future observing software upgrades, especially as Linux becomes more pervasive throughout observing systems. |
|
||||||||||||||||
13.4 Miriad Support ATUC would like clarification on who is providing the 0.2 FTE support for MIRIAD. It appears that support for MIRIAD has decreased. Given that MIRIAD is a mission critical package for the ATNF, we encourage that it be continually supported at a reasonable level i.e. timely responses to bug reports, supported compatibility with new computers and new versions of Linux operating systems. |
|
||||||||||||||||
13.5 ssh ATUC notes comments from users that the lack of the ssh2 software on ATNF computers is making difficult to connect to outside institutions. [Issue raised by users] ATUC requests that ssh2 be installed on the ATNF Unix computers. |
ATNF acknowledges the frustration felt by many users.
A recent meeting between ATNF and senior CSG personnel has established firm milestones for a number of key IT issues that has languished for some time. These include: · Solaris upgrades · Linux support (mainly laptops) · Browser upgrades · ssh upgrade · User account name change over (to CSIRO ident) In particular, the ssh upgrade process will be much simplified by the Solaris upgrade. The present milestone is that the Solaris upgrade will be completed by June 2004. ATNF has also asked CSG to produce (by end March 2004) a plan to implement ssh2 immediately following the Solaris upgrade. |
||||||||||||||||
15.1 Technology Development Report ATUC propose to undertake a review of all projects before the next ATUC meeting. At this meeting ATUC will be willing to advise the ATNF on projects that have such a low priority, in the users view, that they can be dropped from this list. Would the ATNF consider this to be useful input from the ATUC? |
ATUC’s comments would be indeed be valued as part of the priority setting process for new projects. |
||||||||||||||||
16.1 Wide band correlator for Tidbinbilla ATUC suggest that ATNF explore the option of sharing the yet-to-be-constructed wide-band Mopra correlator between Mopra and Tidbinbilla, as an alternative to building two correlators, which will occupy a significant amount of precious time for key engineering personnel. It seems to ATUC that, if possible, sharing a wide-band correlator over the winter season between Mopra and Tidbinbilla may satisfy the demand for such an instrument on both antennas. ATUC would like to see an analysis of the shared correlator idea at its next meeting. |
|
||||||||||||||||
16.2 EoR instrument ATUC can see the value in such an instrument but feel that the scale of the project is more suited to a collaboration between the ATNF and a university department, funded possibly via the ARC. Regardless of the funding, this project could require a significant amount of ATNF engineering effort, which currently is the limiting factor in prioritising new projects. ATUC suggests that engineering support for this project could also be found outside the ATNF, through collaboration with a university department. This project should therefore be a low priority for the ATNF. |
|
||||||||||||||||
16.3 SUSI delay line ATUC also think that this is a very interesting and novel idea. However it appears that this project will be soon rivaled by the planned upgraded wide-band ATCA correlator and any resources would be better spent on this larger and higher priority project. |
|
||||||||||||||||
16.4 Portable VLBI terminal This project should be considered as part of a broader upgrade to LBA facilities. New hardware for New Norcia should only be considered after negotiation with ESA for access to the antenna. |
|
||||||||||||||||
16.5 Pulsar digital filter bank This project should have priority over the upgrade of the existing pulsar correlator to high time resolution. ATUC will review the overall priority of this project along with other existing projects, before the next ATUC meeting. |
|
||||||||||||||||
16.6 Faraday/PHAROS ATNF should provide a project scientist to develop an initial science case, in the event that no especially interested person from the user community steps forward to provide a justification for these instruments. More information on the frequency range that these instruments might operate over would be useful. ATUC will review the overall priority of this project along with other existing projects, before the next ATUC meeting. |
|
||||||||||||||||
16.7 HIFAR This is a very large project. The scientific and technical case for HIFAR should be developed further, in particular how it aligns with LOFAR and the SKA. ATUC will review the overall priority of this project along with other existing projects, before the next ATUC meeting. |
|