The ATNF MNRF upgrade program consists of the following projects:
Project Leader: M.W. Sinclair
Project Scientist: R.N. Manchester
Estimated cost (Jan 1995): $1.625M
Estimated completion date: January 2002
Project Leader: M.W. Sinclair
Project Scientist: B.S. Koribalski (chair)
Estimated cost (Jan 1995) $1.025M
Expected completion date: January 2002
Project Leader: M.J. Kesteven
Project Scientist: B.M. Thomas
Estimated cost (Jan 1995): $0.84M
Estimated completion date: September 1999
This project includes a design study to confirm the optimum atmospheric
phase correction strategy for the ATCA. At this stage we are evaluating
the use of water vapour radiometers operating at either 225 GHz
or 22 GHz.
Construction of four 225GHz WVRs to complement the existing prototype.
Project Leader: P.J. Hall
Project Engineer: G.C. Carrad
Project Scientist: M.H. Wieringa, R.J. Sault
Estimated cost (Jan 1995): $0.148M
Extended completion date: September 2000
NB Not included in this project costs are:
(a) Master frequency standard, e.g. H-maser, and
(b) Any local oscillator modifications to current receiving systems
or any local oscillator units required for new receivers.
Project leader: W.E. Wilson
Project Scientist: J.L. Higdon
Estimated cost (Jan 1995) $0.69M
Estimated completion date: February 2000
Three and a half extra stations will be added to the 3 km arm
of the Compact Array. The AT document (AT31.6.7/012) by J.L. Caswell
and L. Staveley-Smith, can be considered as starting reference.
One of the stations shall have six piers rather than the standard
four, this will enable the telescope to be moved a half a unit
(7.5mm) step, hence the nomenclature.
Project Leader: J.W. Brooks
Project Scientist: J.L. Caswell
Estimated cost (Jan 1995): $0.4M
Estimated completion date: October 1999
Additional manpower support for the development of computer software
for the ATOMS project will be provided under this grant.
Project Leader: D. McConnell
Project Scientist: W.N. Brouw
Estimated cost (Jan 1995): $0.185M
Estimated completion date: April 1999
Project Leader: G.G. Moorey
Project Scientist: J.L. Caswell
Estimated cost (Jan 1995): $0.21M
Estimated completion date: September 1998
This receiver will be the prototype for the 12mm C.A. receivers
and we will probably build two front ends.
(a) The first unit will be a relatively narrowband front end (21-24
GHz) utilising a small dewar with a CTI system 21 cryodyne and
will be mounted on top of the existing 3mm receiver. This will
be installed at Mopra in June 1996 and will be available for VSOP
support.
(b) The second unit will be a standard 12/3.5mm (and possibly
7mm) system and will be installed at a later date. Both systems
will be built under this project's total budget.
Project Leader: M.W. Sinclair
Project Scientist: D.L. Jauncey
Estimated cost (Jan 1995): $0.2M
Estimated completion date: March 2000
Provision of a high precision time and frequency standard for
the ATNF sites.
An additional S-2 tape playback unit will be bought and configured
to increase the VLBI S-2 correlator system (based in Sydney) from
6 to 7 stations.
Five timing units will be constructed for Narrabri, Mopra, Parkes,
Tidbinbilla and Perth. The units will consist of a personal computer
field station (PCFS) plus a GPS receiver (card).
Project Leader: W.E. Wilson
Project Scientist: J.E. Reynolds
Estimated cost (Jan 1995): $0.314K
Estimated completion date: March 1998
Two areas of research that are becoming increasingly important
for the future of radio astronomy are array technology (both focal
and aperture plane) and the need for active frequency excision.
Frequency excision will become increasingly important for the
existing systems and both array technology and frequency excision
are of fundamental importance for the next generation in square
kilometre telescopes.
Project Leader: B.M. Thomas
Project Scientist: R.D. Ekers
Estimated cost (Jan 1995): $140K
Estimated completion date: January 2001
Project Leader: W.E. Wilson
Project Scientist: R.D. Ekers
Estimated cost (Jan 1995): $46K
Estimated completion date: January 2001