Line 19: Line 19:
 04:55:00 Switch to DSS-45  04:55:00 Switch to DSS-45 
  
-04:20:00 adjust gain as IF2 power level on DAS has been low +05:50:00 change backend patching to adjust gain as IF2 power level on DAS has been low  
 + 
 +06:24:20 power looks finally normal after tweaking the patching.  
 + 
 +06:58:01 Fringe confirmed 
 + 
 +14:00:00 End of schedule
  