Problems with CA01, so tie ant 2345 2345 for this run.

phase up on 1934-638 at start of run

08:20UT: concerned phases had drifted out, but all scans were too short to phase up again! Finally got a pcal to work, but fear it made phases worse.

08:27: stop schedule and go to 1934-638 to phase up again. Phases were indeed a long way out. (Actually, not as bad as I had initially though, as vis is showing ca01, but it's not in tied array…)

08:30: back on source in main schedule with nicely phased array.

08:34: finish typing comments in wiki and find ATCA idle! why?!

08:35: ATCA now back on source.