This page will be updated monthly to report the current conditions of the Observatory, and current expectations for data delivery.

Progress of some of the ASKAP Survey Science Projects has been slower than expected due to a range of issues, not limited to delays due to the Setonix system and other upgrades, competing resource allocation, time-consuming calibration, increased solar activity, lower than expected science quality of some data, and inefficient communications between the ATNF and Survey Science Teams. In response, the new ASKAP leadership team paused the existing meetings and communications to the SSTs, temporarily simplified the observing pool to only include those surveys reporting sufficient data quality in the low-band, and commenced a process to meet with the Principal Investigators of teams, and define a path forward to address the current concerns. This path was communicated to the SSTs in June 2025. 

Current Projects in the Observing Pool (July 2025) 

  • EMU/POSSUM
  • VAST Extragalactic

Next Projects in the Observing Pool (August 2025) 

  • WALLABY
  • FLASH
  • VAST Extragalactic

Expected Observing Schedule

This is the expected timeline for the progress of the Survey Science Projects. This timeline aligns with the RASSP recommendations, with an additional year, which extends into 2029. Realisation of this timeline is dependent on on-time delivery of projects under the Key Capabilities program, and no major failures in the telescope or HPC systems. This timeline will be updated monthly to reflect any changes, and these will be communicated to the community. 

SurveyNext dataData at 1 June 25 + 1/4 survey completion*Complete
  Schedule versionV0.2 V0.2 V0.2 
EMU July 2025 mid 2026 mid 2027 
WALLABY Aug 2025 early 2028 late 2029 
FLASH Aug 2025 late 2025 early 2026 
VAST_EXGAL July 2025 late 2025 early 2027 
VAST_GAL Oct 2025 late 2026 mid 2027 
HI_MAG Nov 2025 late 2026 early 2029 
HI_GAL_PLANE Apr 2026 late 2027 early 2029 
HI_MAG_STREAM Oct 2026 late 2027 early 2029 
HI_GC June 2027 mid 2028 late 2029 
DINGO_LOW_Z Sept 2025 late 2026 late 2028 
DINGO_HIGH_Z Sept 2027mid 2029Discussions underway with DINGO team** 
OH_GAL_PLANE Mar 2027 early 2027 mid 2027 
OH_GAL_CENTRE June 2026 mid 2027 mid 2029 
OH_LMC Nov 2026 late 2026 early 2028 
OH_BULGE Feb 2026 early 2026 late 2026 
*Survey completion is intended to be read as the total accepted observing hours from the RASSP review
**Working with DINGO on use of 4-hour observing blocks to expand observing season.

Tasks and progress milestones 

The changes to the software pipelines and processes that underpin this proposed schedule are:

TaskDetailResponsible personExpected completionProgress
Meet with SSP PIs George Hobbs (GH)/Cathryn Trott (CT) to meet with all teams GH/CT June 2025 Completed 
Weekly emails to PIs Progress and plans emails to be sent weekly to PIs of SSPs GH/CT Ongoing Up-to-date 
Firmware upgrade Minimise correlator drop-outs and other issues with spectral line observing modes​Stephen Ord (SO)  September 2025Scoped
Reference field calibration Reduces calibration time, allowing easier band changeSO  August 2025Ready for testing with teams
Direction Dependent Calibration and out-of-field bright source subtraction  SO August 2025Ready for testing with teams