ca-forum#9 - minutes

        (22/5/95)

 

 

 

1.  Digital Synch Demods.

 

      a. The installation work by G.Graves is complete.

 

      b. The units do not work as well as they should, and are

noisy - a factor 2 or so worse than the analogue units.

 

      There appear to be several problems.  If a constant (DC) signal

is input to the DSD we expect to see a constant output, with IN and OFF

equal.  At Narrabri we find an rms of around 6 counts (with mean

counts of 26000);  further, the ON and OFF are anti-correlated;  this

effect is not seen in the lab. at epping, and suggests a problem with

the Narrabri clocking.

 

-->   Ron Beresford will set up an experiment, replacing the

Voltage to Freq unit with a precision oscillator (500 KHz);  the

switching waveform will continue to be derived from the ACC.

This should help localise this aspect of the problem.

 

      If we sum the ON and OFF we find a lower level rms (2-3 counts),

with a further disconcerting pattern:  a steady ramp upwards for

5 or 6 counts, followed by an abrupt fall.

 

 

      The epping tests show a low level noise in the units which

is higher than expected.

 

--> This will be pursued by Mark Leach/Warwick Wilson.

 

 

 

2.  (UVW) modifications.  The task is to ensure that the (UVW)

assigned to a visibility are correct for all samples in a mosaic

observation.  Previously the (UVW) were calculated for the mid-point

of the clock cycle (the nominal integration cycle);  in mosaicing

some fraction of the start of the cycle is blanked while the antenna

is driving;  the (UVW) calculation should reflect this shift in the

mid-point of the actual integration interval.

 

      Changes were made to CAOBS and CACOR.  Numerical checks have

been done.  (The (UVW) derivatives have been checked;  WEW has checked

that the end results are correct).

 

 

3.  Sampler Birdies.

 

G.Baines and W.Wilson carried out a series of tests in an attempt to

understand the extent of the problem.

 

a.  Antenna 6 was worse than the others because the OSP connectors

had been incorrectly assembled (fingers missing).  Once replaced, the

birdies in antenna 6 are at the same level as all the other antennas.

 

The question of whether other antennas also lack these fingers was raised.

The Narrabri array was checked a yera or so ago;  Mopra should be revisited.

 

 

b.  The prognosis for further isolation with better hardware is poor:

the OSP connectors are not much worse than the SMA connectors.

 

    Attempts to prevent the signal getting to the feed are viewed

unfavourably -- we'd need to close the gap between the turret and the

upper vertex room floor, thought to be difficult and unreliable.

Absorber is also seen as unlikely to help greatly.

See reports by G.Graves and R.Gough (AT/31.6.2/025, AT/31.6.3/05

and AT/39.2/055).

 

 

c.  W.Wilson suggests moderating the harmonics in the signals :

 

---> REB will place some low-pass filters in the 128 and 512 MHz lines.

This will be trialled early in the coming month.

 

 

4.  Mosaicing enhancements.  The problem that needed attention was

the difficulty the system had in accomodating to large swings in

system temperature in mosaicing objects such as CenA.

 

D.McC has enlarged the environment space in the ACC.

MJK modified CAOBS so that in mosaicing mode the user can ask to

have environments set automatically - a different number for each field

in the mosaic.  This means that sampler levels and attenuator settings

will be reset separately for each field.  Trials on 8 May indicated that

the system works OK.  The procedure is documented on the web.

 

-->  NEBK will subject the system with exahustive CenA observations in june.

 

 

5.  S-band beam patern assymetries.

 

D.McKay discovered last week that the S-band beam patterns are

asymmetrical -  basically elliptical, different for the two polarisations,

with an apparent squint between the two polarisations - The original

symptom was an offset between the two half-power mid-points.

 

Derek then produced some beam patterns which show the ellipticity of

the patterns;  they also show that the sidelobe structure is bad.

 

Some of the trouble can be traced to the out-of-focus nature of the

S-band installation.

 

Lowering the subreflector to its lowest point improved the sidelobes,

but not the ellipticity;  nor did it appear to cure the squint.

 

It is worth noting that at present the subreflector cannot be

driven under computer control.  This imposes a number of costs:

 

 

a.  There is a loss of about 15% at S-band with the subreflector

locked at the (C/X) position.

 

b.  There is a loss of about 5% at C and X while the subreflector

is at a compromise position between the optimum setting for X

and the optimum for C-band.

 

c.  The beam ellipticities, and the different shapes at the two

polarisations will have disturbing effects for wide field observations

at S-band;  imaging and polarimetry will be affected.

 

Recommendations:

 

      a.  That computer control of the subreflector be implemented.

      (Note that the pace of the subreflector movement is painful -

      3-4 minutes from C/X to the S-band position).

 

The electronics to control the subreflector are complete and installed -

the problem is software, ACC and CAOBS.

 

 

      b.  S-band never be used for pointing checks.

 

      c.  The consequences for mapping and polarimetry be estimated,

      and the general community be advised.

 

 

      d.  It would be useful to examine the Mopra S-band performance

while it has the Seti feed.  There is apparently barely any time for this

test - G.Baines wants to dismantle the feed as soon as the cooperative

program is finished.  The experiment would be brief -- 1 hour of observations,

on a strong source (Virgo ... late afternoon/evening);  there is some

setup .. linear polarisation would need to be restored;  the pointing

dataset would need to be returned. 

 

--> Mal Sinclair/G. Baines/MJK will examine the options.

 

 

5.  X-Y amplitudes.  WEW had found that the amplitudes of the x-y

calibration correlations were unreliable in mosaicing mode.  The

first cycle (when HOLD was applied) seemed correct;  the subsequent

cycles on the same field (when HOLD was zero) were incorrect -

the ON amplitudes decreased, and the OFF amplitudes increased).

(The phases are reported to be OK, although this proposition may

be suspect at L-band).

 

-->  The effect seems to have been traced to the ACC.  DMcC will follow this

up.

 

 

6.  Data Quality observations.

 

( I note that these were an ATUC request from circa 1987;  we're

slow, but we do listen).

 

 

a.  What to observe?

 

  1934-638 or 0823-500 depending n the season.

 

  Two fields will be established for each case - one with the source

a modest offset from the field centre (say 1 arcminute);  and one

at several primary beamwidths away (say 1 degree).

 

The large offset field should be empty.

 

-->  John Reynolds and Neil Killeen will look for suitable positions.

 

 

b.  Frequencies?

 

   The observations should alternate between the two fields, and between

the two major bands:

 

      5 minutes, 1934, at L/S bands

      5 minutes, empty field, at L/S

      5 minutes, 1934, at C/X bands

      5 minutes, empty field, at C/X

 

The observations should run overnight - 12 hours if possible.

 

 

c.  Who should observe? - The duty astronomer.

 

The plan is that these observations should

be scheduled for the last night of the reconfiguration period.  If

the calibration obserevations (baseline and pointing) have failed,

then these data quality observations will be pre-empted.

 

Since these will be fully scheduled observations, the duty astronomer

will be expected to attend and to carry out the observations.

 

 

d.  Who should analyse the data? - The narrabri staff.  Neil Killeen

has volonteered himself and M.Wieringa to prepare a miriad procedure

to process the data.  The load on the observatory staff should then be

tolerable:  they'll have results to review and compare with previous

runs.  There is a complication in that the calibration source will

not be at the phase centre .. N.E.B.K. undertakes to provide the necessary

option in miriad for this.

 

 

 

-----------------------------------------------------------------------

 

I suggest that the next ca-forum be on Tuesday, June 27, 11:00 am.

 

 

A number of figures were shown during the meeting - these are available

on application to M. Kesteven.

 

 

Staff space
Public